Upcoming Release Vehicle Schedules
CloudRouter v4 Targeted Issues And Enhancements
Community CloudRouter 4 Schedule | ||
Planning Phase | ||
09/14/2016 | 09/14/2016 | Community Input / Feature Submission Via Gitter |
09/15/2016 | 09/15/2016 | Create/Update JIRAs |
09/16/2016 | 09/16/2016 | Planning Freeze |
Development Phase | ||
09/19/2015 | 09/19/2016 | Start Development |
09/19/2015 | 09/23/2016 | Bug Fix And Enhancement Effort |
09/23/2016 | 09/23/2016 | Fix Freeze (Testable|Complete) / Packaging and Development Effort Complete |
09/23/2016 | 09/23/2016 | Mass Rebuild |
Testing Phase | ||
09/26/2016 | 09/26/2016 | Deliver Release Candidate to QA for Testing |
09/26/2016 | 09/26/2016 | Release Candidate Testing Begins |
09/28/2016 | 09/28/2016 | Release Candidate Blocker Meeting |
09/30/2016 | 09/30/2016 | End Of Release Candidate Testing |
09/30/2016 | 09/30/2016 | Release Candidate Go/No-Go Meeting |
09/30/2016 | 09/30/2016 | Release Candidate Freeze |
Launch Phase | ||
10/03/2016 | 10/03/2016 | Final Freeze |
10/03/2016 | 10/03/2016 | Submit AMIs To AWS |
10/04/2016 | 10/04/2016 | Stage And Sync Final Release to Mirrors |
10/04/2016 | 10/04/2016 | CloudRouter 4 Final Release Public Availability (GA) |
Archived Schedules
CloudRouter v3 Targeted Issues And Enhancements
Community CloudRouter 3 Schedule | ||
Planning Phase | ||
8/31/2015 | 8/31/2015 | ONOS 'Drake' Release |
9/14/2015 | 9/25/2015 | Start Feature Submission |
9/25/2015 | 9/25/2015 | Announce Feature Submission Closed |
9/26/2015 | 9/27/2015 | Create/Update JIRAs |
10/08/2015 | 10/08/2015 | Planning Freeze |
10/15/2015 | 10/15/2015 | Openstack 'Liberty' Release |
10/27/2015 | 10/27/2015 | Fedora 23 Release |
11/30/2015 | 11/30/2015 | DPDK 2.2 Release |
11/30/2015 | 11/30/2015 | ONOS 'CODE_NAME_TBD' Release |
12/15/2015 | 12/15/2015 | CentOS 7.2 Release [TENTATIVE] |
02/04/2016 | 02/04/2016 | ODL 'Beryllium' Release |
Development Phase | ||
12/07/2015 | 12/07/2015 | Start Development |
12/07/2015 | 01/03/2016 | Bug Fix And Enhancement Effort |
01/13/2016 | 01/13/2016 | Feature Freeze (Testable|Complete) / Packaging and Development Effort Complete |
01/14/2016 | 01/14/2016 | Mass Rebuild |
Testing Phase | ||
01/15/2016 | 01/15/2016 | Deliver Beta to QA for Testing |
01/18/2016 | 01/18/2016 | Internal Beta Testing Begins |
02/08/2016 | 02/08/2016 | Beta Blocker Meeting |
02/09/2016 | 02/09/2016 | Start Internal Beta Security Review |
02/10/2016 | 02/10/2016 | Internal Beta Security Review Complete |
02/10/2016 | 02/10/2016 | End Of Internal Beta Testing |
02/11/2016 | 02/11/2016 | External Beta Go/No-Go Meeting |
02/11/2016 | 02/11/2016 | Internal Beta Freeze |
02/12/2016 | 02/12/2016 | Create Beta Announcement |
02/12/2016 | 02/12/2016 | Announce Beta Freeze Reached |
02/12/2016 | 02/12/2016 | Stage And Sync Beta To Mirrors |
02/12/2016 | 02/12/2016 | Beta Release Public Availability |
Launch Phase | ||
02/13/2016 | 02/13/2016 | Deliver Release Candidate 1 to QA for Testing |
02/13/2016 | 02/19/2016 | Release Candidate Testing |
02/15/2016 | 02/15/2016 | Final Blocker Bug Meeting |
02/19/2016 | 02/19/2016 | End Of Release Candidate Testing |
02/22/2016 | 02/22/2016 | Release Candidate Go/No-Go Meeting [Release Readiness Meeting On Gitter] |
02/24/2016 | 02/24/2016 | Release Candidate Public Available |
02/25/2016 | 02/26/2016 | Start RC Security Review |
02/26/2016 | 02/26/2016 | Security RC Review Complete |
02/26/2016 | 02/26/2016 | Final Freeze |
02/29/2016 | 02/29/2016 | Submit AMIs To AWS |
02/29/2016 | 02/29/2016 | Stage And Sync Final Release to Mirrors |
02/29/2016 | 03/04/2016 | Slip |
03/08/2016 | 03/08/2016 | CloudRouter 3 Final Release Public Availability (GA) |
CloudRouter v2 Targeted Issues And Enhancements
Community CloudRouter 2 Schedule | ||
---|---|---|
Planning Phase | ||
2015-05-26 | 2015-05-26 | Fedora 22 Releases |
2015-06-03 | 2015-06-03 | ONOS 'Cardinal' Releases |
2015-06-09 | 2015-06-15 | Start Feature Submission |
2015-06-09 | 2015-06-09 | Announce Feature Submission Closed |
2015-06-16 | 2015-06-17 | Create/Update JIRAs |
2015-06-17 | 2015-06-17 | Planning Freeze |
Development Phase | ||
2015-06-17 | 2015-06-17 | Start Development |
2015-06-18 | 2015-06-30 | Bug Fix And Enhancement Effort |
2015-06-25 | 2015-06-25 | ODL Lithium Releases |
2015-06-30 | 2015-06-30 | Feature Freeze (Testable|Complete) / Packaging and Development Effort Complete |
2015-07-01 | 2015-07-02 | Mass Rebuild |
Testing Phase | ||
2015-07-02 | 2015-07-02 | Deliver Beta to QA for Testing |
2015-07-03 | 2015-07-09 | Beta Testing |
2015-07-10 | 2015-07-10 | Beta Blocker Meeting |
2015-07-13 | 2015-07-14 | Start Beta Security Review |
2015-07-14 | 2015-07-14 | Beta Security Review Complete |
2015-07-14 | 2015-07-14 | End Of Beta Testing |
2015-07-15 | 2015-07-15 | Beta Go/No-Go Meeting |
2015-07-15 | 2015-07-15 | Beta Freeze |
2015-07-16 | 2015-07-16 | Stage And Sync Beta To Mirrors |
2015-07-16 | 2015-07-16 | Beta Release Public Availability |
2015-07-17 | 2015-08-04 | Community Beta Testing Period |
Launch Phase | ||
2015-08-04 | 2015-08-04 | Deliver Release Candidate to QA for Testing |
2015-08-05 | 2015-08-26 | Release Candidate Testing |
2015-08-26 | 2015-08-26 | Final Blocker Bug Meeting |
2015-08-26 | 2015-08-26 | End Of Release Candidate Testing |
2015-08-27 | 2015-08-27 | Release Candidate Go/No-Go Meeting [Release Readiness Meeting On Gitter] |
2015-08-28 | 2015-08-28 | Stage And Sync Release Candidate to Mirrors |
2015-08-28 | 2015-08-28 | Release Candidate Public Availability |
2015-09-01 | 2015-09-01 | Final Freeze |
2015-09-02 | 2015-09-02 | Stage And Sync Final Release to Mirrors |
2015-09-02 | 2015-09-02 | CloudRouter 2 Final Release Public Availability (GA) |
, multiple selections available,
Related content
CloudRouter Knowledge Base
CloudRouter Knowledge Base
More like this
Meeting Minutes :: Community CloudRouter v3 Release Planning :: 2015-OCT-01
Meeting Minutes :: Community CloudRouter v3 Release Planning :: 2015-OCT-01
More like this
CloudRouter Release Management
CloudRouter Release Management
More like this
Planned Fedora Packages
Planned Fedora Packages
More like this
Smoke Test Plan
Smoke Test Plan
More like this
CR v2 GA -- Fedora Test Results
CR v2 GA -- Fedora Test Results
More like this